Electricity demand growth is on everyone’s mind as data centers, manufacturing, and electrification of vehicles, buildings and industry take hold. According to analysis of utility forecasts from Grid Strategies, peak demand could grow by 128 GW through 2029 – nearly 16 percent growth over five years. But a new report out by Tyler Norris, Tim Profeta, and Dalia Patino-Echeverri at Duke University’s Nicholas Institute for Energy, Environment & Sustainability, Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems, reveals there might be more wiggle room on the grid than we thought. To find out more we spoke with Tyler about electricity demand growth, the findings of his research, and the ever-changing landscape of the energy transition.
***
Brendan: There have been many forecasts from utilities and analysts of very rapid electricity demand growth from data centers. But the recent DeepSeek news highlighted the potential for much more energy-efficient approaches to AI. Where do you think electricity demand growth from data centers is headed, and how certain should we be about the forecasts?
Tyler: This is one of the biggest and most uncertain questions facing the U.S. electric power sector right now, and if anyone has a crystal ball with the correct forecast, they stand to make a fortune in the public markets. I think it’s fair to say nobody really knows. If you’re an electricity regulator attempting to protect ratepayers, you presumably want solutions that hedge against this uncertainty. Large load flexibility is one of those solutions, because it can enable near-term load additions while buying time for regulators to see how the market evolves before approving large expenditures on new electrical infrastructure.
How are utilities and grid operators responding to this growing load today, and what might that mean for costs, reliability and environmental impacts of the grid?
The prevailing response appears to be a crisis mentality in which investor-owned utilities are rushing to invest in new gas-fired power plants and delay planned coal plant retirements. In the country’s largest electricity market, PJM, the system operator is taking the extraordinary step of suspending long-standing market rules to fast-track proposed gas units ahead of other generators. In states like South Carolina, investor-owned utilities have advocated for legislation to override the public utility commission to accelerate combined cycle gas plants. The implications of these steps will vary from market to market, but the general picture is major investment in additional fossil fuel infrastructure that will tend to crowd out other potential investments and shape the power sector for decades.
How does data center demand flexibility change this picture? How big is this opportunity and what are the potential benefits?
A key realization is that our electric power system has already been designed and built to service a few hours of the year when electricity demand spikes during extreme heat waves or cold snaps. But in the vast majority of hours, the system has idle generation and transmission infrastructure. We found that the average load factor (a measure of system utilization) of the U.S. power system is approximately 53 percent, which means that in any given hour, around half of the existing generation and transmission is unused.
This means the existing power system can accommodate large volumes of new load, provided those loads don’t impose additional burden on the system during the highest demand hours. Specifically, our study finds that if new large loads like data centers can curtail their annual electricity consumption by one quarter of one percent (0.25 percent) for short durations, the existing U.S. power system could accommodate up to 76 gigawatts of new load – about a 10 percent expansion in U.S. peak power demand – which exceeds upper-end forecasts for data center additions through the early 2030s. We refer to this as curtailment-enabled headroom.
The potential benefits are wide-ranging. First, it could enable faster interconnection of data centers to the grid, instead of waiting years for upgrades required to deliver more power during extreme peaks. Second, it could buy time to watch how the data center market evolves and hedge against the uncertainty introduced by DeepSeek before committing to more gas infrastructure. Third, it could mitigate growing supply chain constraints for grid equipment like transformers and circuit breakers and enable greater focus on the highest-value system investments. This is before considering benefits related to mitigated stranded asset risk from new fossil fuel infrastructure and its associated emissions.
None of this is to suggest we shouldn’t be investing in transmission expansion and new generation, but rather that targeted flexibility can help integrate new mega-loads in a more methodical manner and enable us to invest limited resources in smarter ways.
Is this potential concentrated in specific regions, and are those regions where tech companies want to build new data centers in the first place?
We found curtailment-enabled headroom in all of the 22 balancing authorities that were analyzed, varying as a share of each system’s peak load based on the utilization rate in its peak season. The largest concentrations were in PJM, MISO, ERCOT, SPP, and Southern Company (i.e., Georgia Power, Alabama Power, and Mississippi Power), which overlap with some of the biggest data center growth markets. The specific headroom figures necessarily represent first-order estimates, and our hope is that it motivates regulators and utilities in each jurisdiction to develop more granular analysis to inform system planning.
What does it mean for a data center’s electricity demand to be flexible? Is this a capability data centers have today or are significant changes needed to enable this as a solution?
Flexibility refers to a customer’s ability to temporarily reduce its electricity consumption from the grid during periods of system stress. Our analysis found that the average duration of curtailment events is approximately two hours, and during 90 percent of these events, at least half of the customer’s load is retained. This suggests a modest degree of flexibility can make a significant contribution.
The first option is if a customer can tap on-site power supply, such as battery storage, renewables, fuel cells, or other fuels. The second is temporal flexibility, where a customer defers a task by a few hours. The third is spatial flexibility, where a computational workload is shifted to a data center in a different location. Finally, there’s the option to simply reduce operations, which is more common among computational loads like bitcoin mining.
A key factor that’s driving more interest in flexibility right now is that computational tasks related to AI model training (e.g., large language models like ChatGPT) appear inherently more deferable and batch-able than traditional on-demand cloud computing tasks, which could unlock more of this capability. The growing prevalence of deferable training workloads is also allowing new data centers to locate in more geographically diverse areas, enabling greater access to renewable power. The cost of on-site battery storage has also declined significantly in recent years.
Why don’t we see more utilities and data center operators pursuing this approach?
A select number of market participants are actively working to scale these capabilities, some of which we highlight in the report. As for why we haven’t seen broader uptake, one interpretation is that advanced computational load-shifting methods, as well as very tight grid supply chain constraints, are relatively new phenomenon and everyone is still catching up. Another interpretation is that some electricity regulators have created incentive structures for utilities to maximize capital expenditures, and for new loads to free ride on existing ratepayers to socialize the cost of new capacity, rather than invest in flexibility.
What can utilities, regulators and policymakers do to encourage demand flexibility from data centers?
At minimum, our hope is that this study will motivate stakeholders to assess the potential for flexibility from new loads in their jurisdiction. Another immediate, straightforward step that regulators can take is to open a proceeding and invite comments from stakeholders on what changes are needed in their jurisdiction to enable this capability. In some cases, new load service tiers similar to PG&E’s Flex Connect program and ERCOT’s Controllable Load Resource service may be necessary. One of the basic challenges is that there are no standardized procedures or form contracts for large load interconnection across the U.S., which has led some experts to call for action from FERC. Of course, progress is more likely to happen to the extent the data center industry and Big Tech companies embrace solutions and advocate for regulatory changes.
Tyler, is there anything we didn’t ask that you think we should? Anything we should know and our readers should know about the state of things?
Our report focused primarily on the opportunity for flexibility from new data centers, but it’s worth emphasizing that flexibility is also possible from other commercial, industrial, and residential customers, including existing loads. You could imagine a case where a new data center prefers to remain inflexible, but instead works with the utility or system operator to procure flexibility from other loads (e.g., as a virtual power plant or distributed capacity procurement) in a way that creates similar system-wide benefits.